WC waste has been fitted and diverted to existing stack at high level in ground floor corridor.
Gas pipes have been capped off. Brentwood School to produce method statement for CDMC.
Basin and shower waste has been dropped below joists to avoid notching. Boxing/false ceiling to doorway lobby to be fitted after construction of staircase perimeter wall.
Waste diverted to main stack via high level drop to corridor. CVA to instruct relocation of light fitting.
Rodding access at stack connection. Boxing to have removable panel to provide access.
Kitchen cold water feed has been traced and confirmed to be separate from bathroom feeds.
Beam cut to allow access to level 1. Timber cut by hand with approximately 1 hour per cut.
50mm retained in situ for future investigation of structure. Conservation to advise on treatment of exposed timber.
Portion of beam retained for conservation officer to inspection and retention.
Dito
Gas pipes have been capped off. Brentwood School to produce method statement for CDMC.
Basin and shower waste has been dropped below joists to avoid notching. Boxing/false ceiling to doorway lobby to be fitted after construction of staircase perimeter wall.
Waste diverted to main stack via high level drop to corridor. CVA to instruct relocation of light fitting.
Rodding access at stack connection. Boxing to have removable panel to provide access.
Kitchen cold water feed has been traced and confirmed to be separate from bathroom feeds.
Beam cut to allow access to level 1. Timber cut by hand with approximately 1 hour per cut.
50mm retained in situ for future investigation of structure. Conservation to advise on treatment of exposed timber.
Portion of beam retained for conservation officer to inspection and retention.
Dito