Thursday, 26 September 2013

Site Visit 25.09.13

 Ducting to common areas still to be completed

 ditto- fire rated access panel to be fitted

 Stair mist coat decoration complete

 Tiling to shower cubicle

 Schluter profile specified not fitted. Mirror to be fitted. Tile to shower upstand to be floor tile- not wall tile. Granitogres tile skirting at same height to perimeter.

 Sink/ tap/ waste fitted/ worktop fitted. 2nd fix electrical to be completed.

 Kitchen carcasses completed.

 Panelling to be cleaned/ repaired/ waxed.

 Old blind fittings to be removed.  New blinds to be fitted- refer to schedule 0352 41.1. Contractors choice- forward details for comment.

  Dishwasher front/ oven and washing machine front to be completed.

 Track lighting fitted

 Pendant cable over dining table area to be lengthened

 Corridor- access panel required to duct formed for AAV adjacent door

 Flush access panel required to stair to replace screwed mdf panel

 GFL wardrobe to be completed

 Architrave to be removed- small/ square profile to be added and redecorated
Shelving to recess not fitted

 Air brick requires cover vent panel- details to be forwarded

Old radiator refitted GFL bedroom adjacent door- to be new only. Remove and replace.

Thursday, 19 September 2013

Site Visit 18.09.13

 GFL Bedroom lining underway


 2nd fix electrical to bedroom adjacent shelf recess

 GFL Main entry door installed

 Stair/ lining
 Cut beam/ stair
 concealed cisten/ wc installation to shower room underway

corridor to 1st floor- area for AAV access

Friday, 13 September 2013

Site Visit 10.09.13

 Bonding plaster used incorrectly to repair over timber beam GFL bedroom

GFL wall/ ceiling awaiting skim coat

Exposed beam to be covered within stair void

 raked lining to stair soffit

 lining poorly constructed to stair- not plumb/ level- condemned

 Ditto

 Conduit removed from existing paneling and paneling subsequently damaged... to be made good

 Services awaiting completion prior to installation of kitchen

 High level duct to be extended for kitchen high level background extract

 Electrical works awaiting completion

Fire rated lining to bedroom still to be completed

 Timber bead over new lining- not as CVA setting out

Kitchen units assembled- awaiting installation

Thursday, 5 September 2013

Site visit 04.09.13


Kitchen to be installed from 05.09.13

 Completion of first fix electrical underway

 Flooring underway to newly formed corridor

 New ceiling board to be installed to bathroom to accommodate recessed lights- CVA to issue AI

 Duct to be formed for extract 1FL

 Footing/ partition to be completed

 2 layers plasterboard/ fire rated access hatch required to formed bulkhead GFL adjacent entry door- CVA to issue AI

 Radiators not as specified- sizes/ type/ model to be checked/ confirmed



Monday, 2 September 2013

Site Visit 30.08.13


 Kitchen electrical outlets are being set out. Rewiring to both levels is underway.


 Ditto

 Ditto

Radiator pipe runs and rewiring has been notched into new joists.


Where stair opening was made fireplace hearth was cut and removed. Carpet to cover as per CVA specification.


Floor infill to stair opening has been constructed with new joists running over existing beam. Noggins connect old joists with new. 


 Existing original beam is visible below joists.


 Cupboard to level 1 has been partitioned off. 


 The demolition of the stair and infill of the floor has created a larger living space. Floor substrate to be completed prior to carpet installation.


 Ditto

 Replastering to hearth wall required.


Durgo installed as per CVA revised drawings. CVA to instruct additional boxing in with inspection hatch to corridor.


At ground floor, partitions are being installed to create bedroom and study space. Partition set out to align with existing beam above. Allowance for electrical and mechanical fixing being made. CVA to confirm fire lining to lobby partitions.


Plasterboard lining to ceiling infill has been installed. Gapping between beam and plasterboard to be filled with plaster.

 
  Ditto

Where existing plaster from original ceiling is present, CVA propose plaster infill (new plaster to adhere to existing)

 Ditto

Staircase has been installed. Timber supporting wall and wall plate to be set out on installed. CVA to confirm whether it will be possible to provide storage space under the stair.

 
Ditto

Foundations to timber wall incomplete. Blockwork is being set out and packed.