Thursday, 5 September 2013

Site visit 04.09.13


Kitchen to be installed from 05.09.13

 Completion of first fix electrical underway

 Flooring underway to newly formed corridor

 New ceiling board to be installed to bathroom to accommodate recessed lights- CVA to issue AI

 Duct to be formed for extract 1FL

 Footing/ partition to be completed

 2 layers plasterboard/ fire rated access hatch required to formed bulkhead GFL adjacent entry door- CVA to issue AI

 Radiators not as specified- sizes/ type/ model to be checked/ confirmed