Thursday, 26 September 2013

Site Visit 25.09.13

 Ducting to common areas still to be completed

 ditto- fire rated access panel to be fitted

 Stair mist coat decoration complete

 Tiling to shower cubicle

 Schluter profile specified not fitted. Mirror to be fitted. Tile to shower upstand to be floor tile- not wall tile. Granitogres tile skirting at same height to perimeter.

 Sink/ tap/ waste fitted/ worktop fitted. 2nd fix electrical to be completed.

 Kitchen carcasses completed.

 Panelling to be cleaned/ repaired/ waxed.

 Old blind fittings to be removed.  New blinds to be fitted- refer to schedule 0352 41.1. Contractors choice- forward details for comment.

  Dishwasher front/ oven and washing machine front to be completed.

 Track lighting fitted

 Pendant cable over dining table area to be lengthened

 Corridor- access panel required to duct formed for AAV adjacent door

 Flush access panel required to stair to replace screwed mdf panel

 GFL wardrobe to be completed

 Architrave to be removed- small/ square profile to be added and redecorated
Shelving to recess not fitted

 Air brick requires cover vent panel- details to be forwarded

Old radiator refitted GFL bedroom adjacent door- to be new only. Remove and replace.