Wednesday, 14 August 2013

Site Visit 14.08.13

 Electrical boxing in to bedroom has been opened up - to be retained as part of contract.

 Radiator pipes are being installed to ground floor accommodation.


Staircase has been retained to provide site access.

Timber paneling is being protected as per the conditions from the conservation officer.


Loose plaster has been removed on the rear surface of the masonry hearth at first floor level. CVA to schedule plastering repairs.


Where partitions have been removed at Level 1 coridoor, walls are to be made good. Plaster to surrounding walls is intact.


Plaster repairs required where kitchen tiling has been removed.


Ventilator to ground floor bedroom is visible where floorboards have been opened up. Radiator pipes are being fitted.


Beam above flat entrance to remain exposed after entrance partitions are installed.


B&H to set out area of ceiling to be removed.


Decorative trims to beam have been removed to allow staircase trimmer to be installed. Plasterboard to be repaired and replaced where required.



Timber structure to entrance surround has been exposed where stud partition has been removed.


Ceiling and floorboards opened up to reveal proposed stair landing point


Column terminates below floorboards at stair landing point


CVA propose to remove plastering to north staircase wall at Level 1 to reduce partition thickness and create even finish to align new level 0 partition.


Ditto
Stair opening stripped in preparation for stair setting out.